----------------------------------------
I have had a lengthy discussion with the road contractor this morning. We have determined that with the weather getting ready to turn cold that we will postpone our paving work until Spring. Many factors have contributed to the work not being able to be done this year.
1. Asplundh was here for 7 weeks clearing power line right of ways.
2.After they left we had a period of 6-8 weeks with 90%+ humidity when the road did not dry, and scattered rainy days that didn't help matters.
3. Finally, in the last 2 weeks the asphalt plant has had mechanical issues limiting/stopping their production. All paving companies in this area pull asphalt from this one plant. Aside from their mechanical issues, incoming cold will stop any work regardless, and the plant always closes down for the season well before Thanksgiving.
The grading work planned for the side roads will be done next week as it is not temperature sensitive. Timing/dates will be passed along as the time nears.
Keith Patton
No comments:
Post a Comment